Please reference the construction timeline to decide the best time to tour.
Date |
Time |
Timeline Description |
| Monday, October 26, 2026 | ||
| Wednesday, November 11, 2026 | ||
| Thursday, November 19, 2026 | ||
| More information to come. | More information to come. | December 2026: Steel structure tops out. Roofing work begins, lower floor finishes begin, upper floors structural walls, wiring, and plumbing put in place. |
| More information to come. | More information to come. | |
| More information to come. | More information to come. | January 2027: The building envelope is closing in, roof HVAC equipment and elevators are going in, and lower floors are nearing completion. |
| More information to come. | More information to come. | |
| More information to come. | More information to come. | February 2027: Â Interior finish work on all levels in progress. The exterior begins to look finished on the west face of the building. |
| More information to come. | More information to come. | |
| More information to come. | More information to come. | March 2027: The project is in its final stretch: permanent grid power is connected; main HVAC systems are turning on. Focus has shifted to final ground-floor interior details and outside site work/landscaping. |
| More information to come. | More information to come. | |
| More information to come. | More information to come. | April 2027:Â Interior flooring and finishes nearing completion, Exterior work ongoing, and site work near completion. |
| More information to come. | More information to come. | |
| More information to come. | More information to come. | May 2027: Final inspections to begin, Interior finishes complete and ready for inspection, exterior signage installed. |
| More information to come. | More information to come. | |
| More information to come. | More information to come. | June 2027: Anticipate the Denver Fire Department giving permission to move in furniture and equipment. |
| More information to come. | More information to come. | |
| More information to come. | More information to come. | July 2027: Notice of Approval of Occupancy |
| More information to come. | More information to come. |